Spring 2024 Wireless Infrastructure Upgrade

Tags wireless wifi

Spring 2024 Wireless Infrastructure Upgrade

Wi-Fi is a primary method by which students, faculty and staff access the campus network and on-line services.  Our existing wireless infrastructure has aged and reached its end of life, and we’ve started work on replacing it with the newest generation of wireless networking technology known as Wi-Fi 6, which will bring several advancements in speed, capacity, efficiency and performance.  Over the next several weeks, a major portion of the work will proceed with replacing the 1200 access points across campus.  We have a schedule listing the buildings and initial dates for replacement.  As things progress, the dates could shift, and we’ll update the schedule accordingly.

Replacement of the access points is straightforward and should take approximately 15 minutes.  The teams will ensure connectivity is working before moving on to their next location.  However, if you experience issues or have any other questions, please contact us

Building AP's Estimated start date Progress
Garner Hall 33 Monday, February 26, 2024 Completed
Wiegand Center/Annex 45 Monday, March 4, 2024 Completed
Twohig Science Center - Wiegand Annex 4 Monday, March 4, 2024 Completed
Thompson Hall 33 Tuesday, March 5, 2024 Completed
Dalton Hall - Dorm - North 44 Monday, March 18, 2024 Completed
Dunspaugh Hall - Dorm - East 40 Tuesday, March 19, 2024 Completed
Sage Hall 49 Tuesday, March 19, 2024 Completed
Browne Hall 47 Tuesday, March 19, 2024 Completed
Weber Hall 85 Wednesday, March 20, 2024 Completed
Flood West Hall 50 Thursday, March 21, 2024 Completed
Renee Mottram Doss (MD) 63 Friday, March 22, 2024 Completed
Bevilacqua (Dominican Hall) 76 Monday, March 25, 2024 Completed
Benincasa 113 Tuesday, March 26, 2024 Completed
Kolasa Hall 118 Wednesday, March 27, 2024 Completed
Library / Monsignor Barry 56 Wednesday, April 3, 2024 Completed
Landon Student Union 41 Thursday, April 4, 2024 Completed
Health and Sports Center (HSC) 26 Friday, April 5, 2024 Completed
Tennis Facility 2 Monday, April 8, 2024 Completed
Soccer field Press box 5 Monday, April 8, 2024 Completed
Softball field bleachers 2 Monday, April 8, 2024 Completed
Baseball field bleachers 2 Monday, April 8, 2024 Completed
Podiatry - CCHMM 12 Wednesday, April 10, 2024 Completed
Dog Track (Ground/Maintnenace Shop) 4 Wednesday, April 10, 2024 Completed
Fine Arts 22 Thursday, April 11, 2024 Completed
Adrian 30 Friday, April 12, 2024 Completed
Andreas 29 Friday, April 12, 2024 Completed
Farrell Hall 16 Monday, April 15, 2024 Completed
Kelley House 20 Monday, April 15, 2024 Completed
Lavoie Hall 17 Monday, April 15, 2024 Completed
Lehman 23 Wednesday, April 17, 2024 Completed
O’Laughlin Hall 22 Thursday, April 18, 2024  
Powers 28 Friday, April 19, 2024  
Rotunda 1 Tuesday, April 23, 2024  
Sienna 22 Tuesday, April 23, 2024  
Broad Auditorium 9 Wednesday, April 24, 2024  
Cor Jesu Chapel 4 Wednesday, April 24, 2024  
11600 Building 8 Wednesday, April 24, 2024  
Hopper Building 4 Wednesday, April 24, 2024  
PACE - Rooney 6 Wednesday, April 24, 2024  
Sim Lab 3 Wednesday, April 24, 2024  
  1214    

 

Was this helpful?
100% helpful - 4 reviews

Details

Article ID: 157561
Created
Fri 3/1/24 5:00 PM
Modified
Fri 4/19/24 8:34 AM